Holes 9-13 These holes are roughed in and the finer details are being completed. Hole 11 & Hole 12 Complete! Overall Progress After 57 days (16 rain days) the contractor […]
La Quinta
Hole 14 The lake is under construction and has had some cement material from the cart paths laid in to shore up slope and erosion protection. Holes 10, 12, 14 […]
Hole 12 has been sculpted and the halfway house has been completely removed. Also, we are placing demolished cart-path material on the edges of the lakes for two important reasons: […]
Week two of the La Quinta Course Drainage Improvement and Renovation project and GreenScapes Six continues to move forward. Safety Reminder For your safety, all community traffic—including walking, biking, and […]
Exciting progress is underway at the La Quinta Golf Course as renovation work begins in earnest! The Golf Course Renovation Update Safety Reminder For your safety, all community traffic—including walking, […]